What is the turnaround time of a permit application?

Over Counter (OTC) Permits – immediate release (can wait in lobby, if mailed/dropped off - up to 1 business day.

Roof, water heater, siding/soffit, sealcoat (no repair work), ac/furnace, irrigation, some valve changes, emergency sewer repair, rooftop hvac.

Residential projects with plan reviews can take 7-10 business days.  There are no expedited permit offerings, applications stay in order of received dates, to remain fair to all applicants.

Commercial plan reviews – up to 20 business days.  There are no expedited permit offerings, applications stay in order of received dates, to remain fair to all applicants.

Show All Answers

1. What form of payment does VVH take?
2. Do I need HOA approval?
3. Do I need to register as a contractor in Vernon Hills?
4. When do permits expire?
5. What are your construction hours?
6. Do I need a Certificate of Insurance?
7. What is a completion (refundable) bond? (Known as a cash bond)
8. What is the turnaround time of a permit application?
9. Do you have options for turning in permits and receiving permits?
10. Do you accept email or faxed applications for residential permits?
11. How do I call in for an inspection?
12. What are the best times to call for questions or inspections?
13. Where can I find the VVH ordinances or county codes?
14. What construction codes are followed within the Village of Vernon Hills?
15. What are permit fees so payment can be made at all at once?
16. How can I speak to an inspector regarding a specific permit question?